|
Marengo’s FDS job at Yandera on
By FRANK ASAELI
MARENGO Mining Ltd has began definitive feasibility study (DFS) activities
at its Yandera project during the quarter ending December last year, with
site visits by the miner’s newly appointed operations manager Grant
Calderwood and representatives from DFS engineers.
Marengo recently awarded a contract to complete a DFS on the Yandera project
to an alliance of leading
Australian-based resource engineering and
construction company GRD Minproc Ltd and URS Australia Pty Ltd, the
Australian arm of international engineering and environmental group, URS
Corp.
This and subsequent visits would give a good appreciation of the project
location, terrain, environmental and cultural interfaces involved.
In addition, a mineral processing and infrastructure options workshop was
held to examine and refine options as highlighted in the previously
completed conceptual mining study.
The components included in this review were road access to the main site,
plant locations, ore transport, concentrate transport, port locations,
tailings disposal, environmental management and community affairs
management.
A number of options had been identified for costing, on a comparative basis
(phase 1), to determine the best options to form the completed DFS (phase
2).
Also during the quarter, negotiations were conducted for the majority of
other subsidiary studies, with these being awarded were mining studies to
Golder Associates (Perth), tailings management to Klohn Crippen Berger
(Brisbane) and environmental management to Coffey Natural Systems
(Brisbane).
It was anticipated that a number of short, technically specialised studies
were likely to be performed by other organisations during the course of the
DFS, which was scheduled for completion by middle of next year.
The DFS was well on course with phase 1 completion due at the end of the
March quarter.
The study management motivation was for diligent technical and commercial
performance to confidently assess the project’s feasibility, thus enabling
the Yandera project to become a significant supplier to the world’s
copper-molybdenum markets.
Meanwhile, the company had maintained a strong cash position with cash
reserves of A$16.556 million (K44 million) at the end of the December
quarter.

|
 |
|
SELLING |
|
Code
|
Notes |
TT |
|
US$ |
0.3405 |
0.3775 |
|
AU$ |
0.3784 |
0.4234 |
|
POUND |
0.1727 |
0.1827 |
|
euro |
0.2305 |
0.2455 |
|
sing$ |
0.4852 |
0.5063 |
|
peso |
13.71 |
14.09 |
| |
|
|
|