Nation
Business

Porgera eyes 1m ounce-level by ’12
But PJV may miss target of 635,000oz this year: Report

By BRIAN GOMEZ in Sydney
THE Porgera mine may not attain anticipated output of 635,000 ounces of gold this year, but could approach a near record million ounce level once again by 2012, according to an authoritative mineral industry consultancy.
An expert report for DRDGold on to the sale of a 20% stake in the Porgera mine by its subsidiary, Emperor Mines, said projected output this year may be optimistic depending on remediation work on the collapsed west wall, due for completion this month.
Last year’s production of 542,000 ounces was “the lowest since the mine opened”.
The report by Behre Dolbear Australia Pty Ltd said the Porgera Joint Venture required major capital expenditures for open pit mining over the next two years for major equipment replacement.
Significant spending was also needed over the next three years for underground development and capital replacement, along with major spending on autoclaves and mills in the processing plant.
BDA said that with work on the west wall nearing completion, costs for the 2008-10 period would return to the lower levels of Stage 5 mining but would increase again as waste haulage increased with implementation of the Stage 6 cutback.
Based on the latest PJV review of the remaining operating life at Porgera, BDA estimated that direct cash costs per ounce of production would rise from US$401 (K1,065) this year (assuming output of 635,000 ounces) to US$403/oz next year.
As production reaches an estimated peak of 930,000 ounces in 2012 these costs will fall to US$278 (K738.58) an ounce and remain at between US$244 (K648.26) and US$368 (K977.63) in the succeeding three years.
However, this forecast is conservative due to higher than anticipated gold recovery, higher potential gold content in the open pit and the likelihood of increased underground production.
The report said open pit mining would continue until 2016 based on the Stage 6 cutback “and significantly longer should a future decision be made to proceed with Stage 7”.
Reconciliation data suggested that PJV may be underestimating in-pit mineable reserves by at least 10% to 15% contained gold, translating to an additional million ounces of contained gold.
Current reserves are estimated at 9.4 million ounces with additional indicated and inferred resource of 3.6 million ounces.
Underground reserves are estimated at 8.1 million tonnes averaging 8.7 g/t gold with production peaking at around 1.3 million tonnes a year between2013 and 2015.
However, if sufficient reserves are defined “there is good potential to increase underground production up to two million tonnes per annum within three years”.
In recent years gold recovery levels have exceeded budget projections by 2% to 4%. For example, gold recovery last year was 88.4% compared with a budget of 85.6%.
The report also noted that allocation of funds to PJV’s community affairs programme amounted to US$38 million (K100.96 million) over the next seven years, with mine closure costs estimated at US$54 million (K143.46 million).

 

           



 

Sports
Editorial
Column
Letters

Journey to Paradise

 
Bottom Line  
The Notebook
Building Blocks  
Talking Point  
My Say  
Asia watch  
Focus  
 
Weekender  
 
Printing  
Yearbook
Classifieds
Advertising
Web Designing  
 
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   

Copyright © 2003 [The National Online] Private Policy