Nation
Business

K1b benefit package for Ok Tedi villagers

OTML windfall four times better than the previous one

By FRANK ASAELI
PEOPLE living downstream of the Ok Tedi Mining Ltd will receive a benefit package of over K1 billion and four times better that the previous one.
The total benefits package, including those to be provided by the other key stakeholders (PNG Sustainable Development Program and the PNG Government), was estimated at K1.01 billion (US$342 million) over the seven years to 2013.
Negotiations were successfully concluded during the second quarter results ending June 30, 2007 with the communities downstream of the mine concerning the new benefits they would receive from the company.
OTML reported in the second quarter results that export shipments of copper and gold concentrates were 5% higher for the second quarter of this year than the same period last year.
However, copper and gold production for the quarter was 23% and 24% lower respectively compared to that of the corresponding quarter for 2006.
Production for the first half of the year was 17% lower for copper and 16% lower for gold compared to the same period for 2006 because production was impacted by a combination of lower ore grades and throughput.
Results showed that there were no navigability constraints in the Fly River system as rainfall was high for the first half of the year.
Work has also commenced on the process plant building for the mine waste and tailings project to extract pyrite from mill tailings and pipe to the storage area near the lower Ok Tedi.
Half of the line pipe has been received on site and dredging of the access channel to the storage site is about 50% complete with designing reaching 70%.
This has resulted in commitments of US$88.3 million (K267.58 million) or 57% of the current forecast total cost of US$153.6 million (K465.45 million) and the targeted completion date remains as the 2nd quarter of 2008.
A total of 66 people have been recruited by the project team as personnel and contractor personnel in the mobilisation and site set up for the construction of the process plant and the pipeline.

 

           



 

Sports
Editorial
Column
Letters

Journey to Paradise

 
Bottom Line  
The Notebook
Talking Point  
My Say  
Asia watch  
Focus  
 
Weekender  
 
Printing  
Yearbook
Classifieds
Advertising
Web Designing  
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Copyright © 2003 [The National Online] Private Policy