By GYNNIE KERO
Oil Search Ltd is confident the APEC Haus taking shape in Port Moresby will be completed well before the contracted deadline – July 31.
Its construction at Ela Beach is paid for through Oil Search’s tax credit scheme for K120 million and Construction Project Build (CPB) Company is leading the work.
APEC Haus project manager Peter Kearsley said 65 per cent of the building was completed.
“Yes, the project is on budget,” he said. “The next thing you will see is glass go up at the start of February.
“Now having had the roof on, we are able to work on the ground floor.
“Contracted deadline is July 31, the guys will definitely beat that. It will be finished before the end of July.”
Prime Minister Peter O’Neill yesterday said APEC Haus would be converted into a world-class museum after the leaders’ meeting in November.
He also highlighted that more than 80 per cent of the project workers were locals. “Many of our artefact, thousands of years old and held in museums (elsewhere), we want to bring back here,” O’Neill said.